Homestake Meeting, 09/04/14
Attending:
Homestake wiki: https://zzz.physics.umn.edu/groups/homestake/home
Our agenda:
1) Next visit to Homestake: Sep 21-27, six people (Gary, Victor, Daniel, Tanner, Pat, Vuk). Rough plan for the first 3 days:
Tanner to work with Jamey on GPS system. Not sure if this will happen, transceivers won't reach us by then, maybe we can use the prototypes.
Gary and Pat to work on the surface stations.
Daniel, Victor, Vuk to work on underground stations: 4850 2-4, 4100-2, 1700-1.
Ongoing work on 4850 near 17-ledge, so can't work on the 4850-1. It looks like this will go on until the end of the year, and similar for the remaining 1700 stations.
Fiber and many other components have been delivered, foam panels have been delivered.
Plan to do some shopping in Minneapolis next week, in preparation for the trip. Will drive from MSP to Homestake, so can take these with us.
2) UMN test setup (Tanner)
3) Analysis of existing data
Estimation algorithms (Shivaraj, Eric, Noah)